week 14 spring 2018

This week, more detailed and calculated FEA analysis is conducted. I setup a word file. The link is https://drive.google.com/open?id=1xC-1DClN5L0nj40wbD66ZfUY0WL9ha3i

week 12&13 spring 2018

Image
A few FEA are conducted in these two weeks. These FEA tests focused on the load arm reaction when applied real life situation. a 10 Kn load is added on the bottom of the load arm. The material I choose have the maximum yield strength 3.5*10^8 Pa. For the top structure, a load of 5Kn is added. the force is caused to the turning at maximum speed.

week 11 spring 2018

Image
More parts are ordered. We get the ball bearings , wheels, screws.

week 10 spring 2018

Image
This week, the control team get their motor shipped in. I'm able to take some measurement from the real motor and design a motor mount.

week 8&9 spring 2018

These two weeks, I did few FEA analysis on the current design. There are parts being purchased. At this moment. I'm heavily depend on Dan to publish his new design and ideas on building this bogie.